Basic Information
Location (Province): Hubei
Location (City): Xiangyang
Drilling Rig Model: SJW-60 high-pressure jet grouting rig
Drilling Tool Configuration: 89 triple jet grouting drill pipe
Process Type: Jet grouting for seepage control
Construction Process: Single-fluid jet grouting
Stratum Condition: Soil layer
Construction Angle (°): 90
Hole Diameter (mm): 500
Hole Depth (m): 7.2
Construction Efficiency (min): 25
Construction Process
1. Level the site and mark the hole positions;
2. After the rig is in position, adjust the verticality of the mast using the outriggers;
3. Test the operation of the grouting pump and conduct a trial spray;
4. Rapidly drill the connected drill pipe to the required predetermined depth, then perform jet grouting with a lifting speed of 250-300 mm/min, rotation speed of 15-18 r/min, and pump pressure of 16-20 MPa;
5. The high-mast jet grouting rig does not require disassembly of the drill pipe during lifting; observe the grout return condition;
6. When the drill pipe is lifted to about one meter from the hole opening, stop grouting and pull out the drill pipe;
7. Move the rig to the next hole position;
8. Note that the drill pipe does not need frequent flushing; flush once before noon or before leaving work at night, and clean it thoroughly.
——Auman Drilling Rig After-sales Service: Hua Ting